Welcome to Assignment Heroes

It 270

It 270.

College of Computing and Informatics

Name: ### CRN: ###

ID: ###

Assignment # 1 Deadline: Thursday 07/11/2019 @ 23:59

[Total Mark for this Assignment is 6]

IT Project Management

IT270

Instructions:

You must submit two separate copies (one Word file and one PDF file) using

the Assignment Template on Blackboard via the allocated folder. These files

must not be in compressed format.

It is your responsibility to check and make sure that you have uploaded both

the correct files.

Zero make will be given if you try to bypass the SafeAssing (e.g. misspell words,

remove spaces between words, hide characters, use different character sets or

languages other than English or any kind of manipulation).

Email submission will not be accepted.

You are advised to make your work clear and well-presented, marks may be

reduced for poor presentation. This includes filling your information on the cover

page.

You MUST show all your work, and text must not be converted into an image,

unless specified otherwise by the question.

Pg. 1

Question Two

Pg. 2

Question Two

Question One Discuss the need for organizing the project management task into different knowledge areas

containing processes belonging to different process groups (initiating, planning, executing,

Monitoring and Controlling, Closing). Identify and discuss the strengths and weaknesses in the

Project Management Framework shown in the Figure below.

Learning

Outcome(s):

LO4

1 Mark

Pg. 3

Question Two

Question Two Using information about the estimated costs, estimated benefits and a discount rate of 9% for

Project XYZ, calculate the discount factor for each year, the discounted costs, the discounted

benefits, the return-on-investment (ROI) and the net-present value (NPV). In which year does the

payback occurs?

Year Total

0 1 2 3 4 5

Estimated Costs 175,000 22,500 22,500 22,500 22,500 22,500

Discount Factor ? ? ? ? ? ?

Discounted Costs ? ? ? ? ? ? ?

Estimated Benefits 0 80,000 80,000 80,000 80,000 80,000

Discount Factor ? ? ? ? ? ?

Discounted Benefits ? ? ? ? ? ? ?

Discounted Benefits –

Costs ? ? ? ? ? ? ?

Cumulative Benefits –

Costs ? ? ? ? ? ?

Return on Investment

(ROI) ?

Learning

Outcome(s):

LO3

2 Marks

Pg. 4

Question Two

Pg. 5

Question Two

Question Three The traffic control system inside Riyadh city is not meeting the expectations of the city traffic police. The system is

to be updated within a few weeks to incorporate the traffic intensity, the weather conditions and the VIP movements

etc. The entire project is to be completed within 10 weeks as per the following schedule:

Task

ID Task

Allocated

Time

(Weeks)

Budge

t

(SAR)

TID-10 Requirements elicitation 1 10,000

TID-11 Use-case Development 1 10,000

TID-12 Process Model

Development 1 10,000

TID-13 Data Model Development 1 10,000

TID-20 Architecture-Level Design 1 10,000

TID-21 User-Interface Design 1 10,000

TID-22 Algorithm Design 1 10,000

TID-23 Data Storage Design 1 10,000

TID-30 Programming 1 10,000

TID-31 Quality Assurance 1 10,000

At the end of Week 7 of the project you have completed only first six tasks (i.e. you just finished, TID-21 i.e. Data

Model Development) with a total of SAR 67,500 spent to date. The Interior Minister asks you to produce a report on

the status of project work with the help of earned value method. In particular you are asked to include answers to the

following questions in your report:

a. What is the cost variance (CV), cost performance index (CPI), schedule variance (SV) and schedule

performance index (SPI) for the project so far?

b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better

or worse than planned?

d. Use the SPI to estimate how long it will take to finish this project.

Use the earned value management (EVM) in the given scenario answering each of the abovementioned question

separately.

Learning

Outcome(s):

LO3

2 Marks

Pg. 6

Question Two

Pg. 7

Question Two

Question Four Assume the following about Project XYZ

Activi

ty

Duratio

n

(Days)

Predecessor

Activity

A 3 –

B 5 A

C 7 A

D 10 B

E 5 C

F 4 D, E

Draw a network diagram for this project, find the critical path, the critical activities and the project completion time.

Learning

Outcome(s):

LO7

1 Mark

It 270

Solution:

15% off for this assignment.

Our Prices Start at $11.99. As Our First Client, Use Coupon Code GET15 to claim 15% Discount This Month!!

Why US?

100% Confidentiality

Information about customers is confidential and never disclosed to third parties.

Timely Delivery

No missed deadlines – 97% of assignments are completed in time.

Original Writing

We complete all papers from scratch. You can get a plagiarism report.

Money Back

If you are convinced that our writer has not followed your requirements, feel free to ask for a refund.